CPV Woodbridge Energy Center
Location
Woodbridge Township, New Jersey
System Information
2×1 Combined-Cycle Power Plant
Featuring Two GE Fast-Start 7F 5-Series Gas Turbines And A D-11A Steam Turbine With Associated Generators
Total Installed Capacity
725 MW
Supply Capacity
700,000 Homes
Investment
$843 Million
Local And Regional Employment
22 Full-Time Plant Staff And Approximately 75 Ancillary Jobs
600+ Union Labor Workers Over 28-Month Construction Period
In Operation Since
January 2016
PROJECT OVERVIEW
The CPV Woodbridge Energy Center (CPV Woodbridge) generates enough reliable electricity on average to power more than 700,000 New Jersey homes and offset carbon dioxide emissions equivalent of taking more than 1.4 million cars off the road each year. Through our use of General Electric’s (GE) advanced power generation technology, CPV Woodbridge provides safe, reliable, cost-effective and environmentally responsible power for NJ. CPV Woodbridge pairs well with less reliable power sources like wind and solar because it provides a backstop to maintain grid reliability when the wind or sun cuts out.
Phone Inquiries: (877) 355-7010
LEARN MORE
Through Displacement Of Less Efficient Generation, CPV Woodbridge Energy Center Has Avoided:
8,243,428
Tons Of CO2
12,875
Tons Of NOx
13,300
Tons Of SO2